Relevant regulations on calculation of contract price adjustment for mine engineering projects

The contents of the engineering change and related contract price adjustment principles include:
1. The construction drawings (including design changes) in the construction are inconsistent with the characteristic description of the project quantity list, and the comprehensive unit price of the corresponding engineering quantity list items should be re-determined according to the actual construction project characteristics, and the contract price should be adjusted.
2. When the project price list item or its engineering quantity changes due to engineering changes, it should be adjusted according to the following regulations:
(1) If there is any project that is applicable to the change project in the list of marked price, the unit price of the project shall be adopted and determined according to the comprehensive unit price already in the contract;
(2) If the listed price list is not applicable but has a similar project, the unit price of similar items may be referred to within a reasonable range;
(3) If the listed project quantity list is not applicable or is not similar to the change project, the contractor shall propose to change according to the changed project data, measurement rules and pricing method, the information price issued by the project cost management organization and the contractor's quotation fluctuation rate. The unit price of the project is adjusted after the package is confirmed.
The contractor's quotation fluctuation rate can be calculated according to the different calculation formulas of the bidding project and the non-tendering project.
(4) If the price of the listed project quantity is not applicable or similar to the change project, and the price of the information issued by the project cost management organization is insufficient, the contractor shall change the project data, measurement rules, pricing method and market survey. Obtain a unit price for a project that has a legal basis, and adjust the unit price of the project.
3. When the engineering change causes the construction plan to change and the measures are changed, if the contractor proposes to adjust the project cost, the proposed plan shall be submitted to the contractor for confirmation in advance, and the changes compared with the original program measures shall be specified. Happening. The proposed plan shall be implemented after confirmation by both parties to the contract, and the project cost shall be adjusted in accordance with the regulations.
4. For the bidding project quantity list item, when the actual engineering quantity to be calculated and the deviation of the bidding quantity list and the engineering quantity change cause the deviation of the engineering quantity more than 15%, adjustment can be made. When the engineering quantity increases by more than 15%, the comprehensive unit price of the added part of the engineering quantity should be lowered; when the engineering quantity is reduced by 15%, the comprehensive unit price of the remaining part of the engineering quantity after the reduction should be increased.
5. During the performance of the contract, when the price of the contract is affected by fluctuations in the price of labor, materials, engineering equipment and machinery, the contract price shall be adjusted according to the contract.

cooling mold Chiller

The chiller is a cooling water equipment that can provide constant temperature, constant flow and constant pressure. The industrial water chiller can always output ice water that is lower than the ambient temperature. It can be used wherever cooling is needed, either directly or indirectly. The chiller can be used to cool the injection mold and improve the quality of plastic products; Vacuum coating cooling, control the temperature of vacuum coating machine; Food industry cooling, rapid cooling processing; Chemical industry, effectively control the temperature of chemicals; Building cooling, rapid cooling and condensation of concrete, etc. Water chillers are widely used.



Water chillers can be divided into industrial water chiller, screw water chiller, electroplating water chiller, oxidation water chiller, laser water chiller, coating water chiller, wave soldering water chiller, reflow soldering water chiller, exposure machine water chiller, developer water chiller, ultrasonic water chiller, extruder water chiller, high-frequency quenching water chiller, Injection Molding Machine water chiller, electrophoresis paint water chiller Pharmaceutical special water chiller, food special water chiller, stainless steel water chiller, circuit board water chiller, plastic suction machine special water chiller, chemical water chiller, coating water chiller. According to working conditions, it can also be divided into air-cooled water chiller, water-cooled water chiller, low-temperature water chiller, thermostatic water chiller, etc



Energy saving function of water chiller:



The water chiller is a kind of refrigeration equipment that cools water and recycles it. The cooling water temperature can be adjusted automatically according to the requirements, almost without water consumption. Long-term use can save a lot of water. Therefore, compared with the mode of using tap water discharge to cool the equipment, the industrial water chiller is an ideal equipment that can quickly achieve the desired cooling effect and save energy.



About the function of the chiller, I will introduce it here today. Chillers play an important role in industrial production. Enterprises use chillers to improve production efficiency, ensure product quality and increase profits.



1. Regularly check whether the voltage and electric flow of the water-cooled chiller are stable, and whether the compressor operates normally. If it is a semi-closed compressor, regularly check the oil volume, which should be more than 2/3 of the window. When the water-cooled chiller works normally, the voltage is 380V and the current is within the range of 11A-15A.





2. Regularly check whether the refrigerant of the water-cooled water chiller has leakage: it can be determined by referring to the parameters displayed on the high and low pressure gauge on the front panel of the host. According to the temperature change of air temperature (winter and summer), the pressure display of the water chiller is also different. When the water chiller works normally, the high pressure display is 11-17kg, and the low pressure display is 3.5kg-5kg, which are normal.



3. Check whether the cooling water system of the water-cooled water chiller is normal, whether the fan and sprinkling shaft of the cooling water tower are in good operation, and whether the make-up water of the built-in water tank of the water-cooled water chiller is normal. The water-cooled chiller should be replaced with new water once every three months. If it cannot be replaced, please add rust remover.



4. All industrial water chillers should be cleaned once a year when they are used for six months. The main cleaning parts include cooling water tower, cooling water pipe and condenser to ensure better cooling effect.



5. When the water-cooled chiller is not used for a long time, the circuit switches such as the main power supply of the water pump, compressor and Cooling Tower should be turned off in time. The water-cooled water chiller needs to be connected with the cooling water tower and the circulating water pump to achieve the cooling effect. In order to ensure the quality of the circulating water, it can be considered to install a Y-type filter at the water source and add algaecide and scale remover to the cooling water tower to prevent impurities from entering the pipeline and affecting the operation of the unit.

Cooling Mold Chiller,Injection Molding Chiller,Chiller Used In Injection Molding,Cooling Mold Chiller

Ningbo Chenwei Machinery Technology Co.,Ltd , https://www.chenweimachinery.com